Analysis Plans
Last update: 15 May 06
Back to the TWIST 2004 Analysis Page.
Analysis Plan 2006 Data
Slides from the 12 May Software meeting. Items in red are high
priority.
Analysis Plan 2005 Data
Analysis Plan 2004 Data
The remainder of this page is obsolete and applies to the analysis
of the 2004 data.
The following outputs are produced using the OpenWorkbench program,
which has been installed on tnt2k.
Ask Dick or Blair for instructions to access.
Gantt Chart
The Gantt chart has been reduced to fit on two pages, so it is now readable,
but it is intended mostly to give
an impression of the overall flow of
the project. The lines do match those in the task list below.
Task List
The task list now includes a column for task status.
Please note omissions or changes that are needed. The time
intervals are still estimates.